Building a new home from the ground up requires navigating British Columbia's most comprehensive municipal permit pipeline. From initial zoning and geotechnical due diligence to BC Energy Step Code compliance, structural engineering, and full 15-stage construction inspections, here is the complete roadmap to getting your new build approved and built across BC.

New Build Permit Process at a Glance

An overview of the activities, consultant roles, and deliverables required to secure a building permit for new residential construction in BC.

Step & LeadKey ActivitiesPrimary Deliverable
1. Feasibility & Zoning
Canadian Blueprint & Client
Zoning bylaws, setback verification, Floor Area Ratio (FAR), geotechnical soil review, and BCLS legal survey.Project Feasibility & Zoning Assessment Report
2. Building Design & Drafting
Canadian Blueprint
Custom floor plans, structural layouts, exterior elevations, window-to-wall ratios, and spatial calculations.Complete Conceptual & Permit Draft Set
3. 3D Visualization
Canadian Blueprint
Photorealistic 3D rendering and interactive virtual walkthrough to finalize interior/exterior sightlines.Interactive 3D Virtual Model
4. Engineering & Blueprint
CBP & Professional Engineers
Structural engineering (Schedule B), Energy Step Code modeling, mechanical HVAC, and single-layer vector PDFs.100% Intake-Ready Permit Drawing Set
5. Portal Review & Approval
City Examiners & CBP
Digital portal submission, 3–5 day pre-screen, intake fees, plan review deficiency cycles, and stamped permit release.Approved City-Stamped Building Permit

Project Roadmap & Scope of Work

Select a phase below to jump to the details

  1. 1
    Feasibility & Zoning Due Diligence
  2. 2
    Building Permit & Code Design
  3. 3
    3D Virtual Modeling
  4. 4
    Permit Package & Engineering
  5. 5
    Municipal Intake & Plan Review

Overview & Context

Overview

Building a new custom home, infill laneway house, duplex, or multi-unit residential multiplex is one of the highest-value investments a property owner can make. However, new construction also involves the most rigorous municipal oversight in British Columbia.

Every new build must comply with local zoning bylaws, the BC Building Code, and the BC Energy Step Code. Here is how the permit process works and what is required at every milestone.

What Is Required for a New Build Permit (vs. Renovations)

Overview

Unlike interior renovations, new construction touches every part of the municipal regulatory framework:

Requirement Category New Custom Home / Multiplex Interior Renovation (For Comparison)
BCLS Legal Property Survey Mandatory: Establishes setbacks, property lines, and foundation form limits. Not Required unless expanding the footprint.
Geotechnical Soil Report Mandatory: Confirms bearing soil capacity and water table depth. Not Required for standard interior work.
BC Energy Step Code & Blower Door Mandatory: Mid-construction & post-construction airtightness testing. Not Required for minor interior remodels.
Foundation & Groundwork Inspections Mandatory: Excavation, footings, BCLS forms survey, drain tile, and under-slab poly. Not Required (existing foundation remains).
Development Cost Charges (DCCs) Mandatory: Municipal infrastructure fees assessed on new dwelling units. Exempt for single-family renovations.
Full Occupancy Certificate Mandatory: Formal municipal sign-off before anyone can legally move in. Trade final sign-offs only.

Step 1: Feasibility & Zoning Due Diligence

Phase 01

Before design lines are drawn, we conduct a forensic review of your property’s legal and zoning constraints:

  • Zoning Bylaw Compliance: Calculating maximum allowable Floor Area Ratio (FAR / FSR), lot coverage percentages, front/rear/side setbacks, and building height envelopes.
  • Development Permit Areas (DPAs): Verifying if your property triggers environmental, riparian (watercourse), geotechnical hazard, or wildfire protection guidelines.
  • LTSA Title Search & Encumbrances: Reviewing statutory rights-of-way, municipal easements, and private covenants. Learn how to order these in our BC Land Title Search Guide.
  • BCLS Land Survey & Geotechnical Engineering: Coordinating legal boundary mapping and soil bearing tests to ensure a safe foundation design.
Zoning & Site Plan Certified permit site plan sheet for BC custom home permit
Zoning Feasibility & Site Plan: Calculating lot coverage, setbacks, driveway access, and building envelope parameters before permit design begins.

Step 2: Building Permit & Code Design

Phase 02

With site boundaries defined, Canadian Blueprint designs your custom home or multiplex to balance your lifestyle vision with strict building code compliance:

  • Custom Floor Layouts: Optimizing room dimensions, natural daylighting, open-concept living, and functional traffic flow.
  • Secondary Suites & Multiplex Units: For multi-unit multiplexes, designing independent private entrances, sound-insulated shared walls (STC 50+ rating), and discrete mechanical utilities.
  • Exterior Elevations & Massing: Balancing modern curb appeal with municipal neighborhood character and solar orientation guidelines.
Custom Home & Infill Custom home exterior elevations and floor plans
Building Floor Plan & Massing: Designing custom living layouts, private suite entrances, and sound-rated wall assemblies aligned with municipal character guidelines.

Step 3: 3D Virtual Modeling

Phase 03

Experiencing your space before breaking ground prevents costly on-site change orders during framing:

  • Virtual Walkthroughs: Explore every room, test sightlines, review kitchen island clearances, and verify ceiling heights in full 3D.
  • Multiplex & Infill Optimization: Visualize exterior massing, parking access, and outdoor amenity spaces to ensure maximum tenant or buyer appeal.

Step 4: Permit Package & Engineering

Phase 04

With design approved, Canadian Blueprint engineers the complete construction blueprint package:

  • Detailed Cross-Sections & Wall Assemblies: Specifying high-performance insulation values (RSI / R-values), continuous air barrier membranes, and rain screen drainage details.
  • BC Energy Step Code Compliance: Coordinating with a Certified Energy Advisor (CEA) to ensure your home meets municipal Step Code targets (Step 3, 4, or Net Zero Ready).
  • Structural Engineering (Schedule B): Coordinating with registered structural engineers for point load sizing, steel beams, shear walls, and foundation reinforcement.
Engineered Wall Assembly Permit cross section blueprint and assembly details sheet
Detailed Cross Section & Code Details: Vertical assemblies specifying continuous insulation, foundation footing connections, and BC Energy Step Code targets.

Step 5: Municipal Intake & Plan Review

Phase 05

We package your entire submission into intake-ready, single-layer vector PDFs formatted to your municipality's exact naming standards:

Construction Phase: Mandatory Site Inspections

Guide

Once your permit is issued and stamped drawings are printed for the jobsite, construction proceeds through sequential inspection stages:

1. Sub-Slab & Foundations: Excavation, footings, foundation forms with BCLS survey, drain tile, and under-slab poly. 2. Exterior Envelope: Wall sheathing, rain screen drainage mockups, and stucco wire/scratch coats. 3. Rough-In Trades & Framing: Electrical rough-in, plumbing DWV pressure tests, HVAC ducts, and structural framing. 4. Thermal Envelope & Fire Safety: Mid-construction blower door airtightness test, insulation, vapour barrier, and fire-rated drywall between units. 5. Final Inspections & Occupancy: Post-construction blower door report, final plumbing/building sign-offs, and issuance of the Occupancy Certificate.

For a detailed stage-by-stage guide on what inspectors check at each milestone, read our New Custom Home & Multiplex Inspections Checklist.

Start Your New Build Today

Guide

From custom single-family homes to modern multiplex infill developments, Canadian Blueprint provides complete building permit drafting, engineering coordination, and permit navigation across British Columbia.

Canadian Blueprint Logo

Canadian Blueprint Inc.

BC Building Design & Permit Drawings

Published • Updated

Back to Guides

Let's Get Started

Take the next step in your building journey with our specialized design and permit services.

Residential
Homes, suites & outbuildings
  • As-Built Measuring
  • New Custom Homes
  • Home Renovations
  • SSMUH / Multiplex
  • Accessory Buildings & Garages
  • 3D Visualization
Learn More →
SSMUH / Multiplex
Small-Scale Multi-Unit Housing
  • Zoning Optimization
  • Density Bonus Analysis
  • Site Planning
  • Unit Layouts
  • Parking Solutions
  • Permit Strategy
Learn More →